What's being built
- A $2.0M industrial project: Erection of a new structure · Rural industry · Agricultural produce industry.
- Lodged 10 Feb 2025 with Bland Shire Council
- determined 14 Aug 2025.
The basics
Project value
$2,000,000
Declared
Est. end value
$2.9M–$4.0M
Estimate · rough, from project cost
Who's involved
0 partiesNo parties have been identified for this project yet — check back soon, as more become available over time.
Documents
0 PDFsNo documents are available for this project yet — check back soon, as more become available over time.
More development around Barmedman
71 DAs were lodged with Bland Shire Council in the last 12 months, a typical decision takes about 43 days.